Stormwater Drainage Works

As part of Ballina Shire Council’s capital works program, the rehabilitation of stormwater drainage pipes will take place at various locations in Ballina and Lennox Head throughout June and July 2021. 

The rehabilitation works will involve accessing stormwater pipes through existing manholes, cleaning and relining the pipes.

The works will be completed in two stages:

  • Stage One: Initial cleaning, involving jetting and pipe preparation for relining. Duration: one to two days per site.  
  • Stage Two: Commence relining of pipes. Duration: approximately one week per site. 

The following schedule indicates commencement dates for each site, these are subject to change, depending on weather and tide conditions.

Site Commencement date
for cleaning
Commencement date
for relining

Portion 1 – Dodge Lane, Lennox Head

completed

in progress

Portion 2 – Moon Street, Ballina

completed

1-5 and 8 August

Portion 3 – Quays Drive, West Ballina

completed

in progress

Portion 4 – Kerr St, Ballina

2 August

6 August

Portion 5 – Riverside Drive, West Ballina

completed

11 August

Portion 6 – Bangalow Road, Ballina

completed

12 August

Portion 7 – Grant Street, Ballina

completed

1-5 and 8 August

Portion 8 – Tresise Place, Lennox Head

completed

N/A

Portion 9 – Emily Place, Alison Avenue and Patricia Parade, Lennox Head

completed

in progress

Portion 10 – Gibbon Street, Lennox Head

completed

completed

Portion 11 – Alison Avenue, Lennox Head

completed

TBC

Portion 12 – Bayview Drive, East Ballina

3 August

10 August

Portion 13 – Pelican Place, East Ballina

completed

completed

Portion 14 – Spinaker Crescent, West Ballina

completed

completed

Portion 15 – Martin Street, Ballina

3 August

7 August

Portion 16 – Dolphin Drive, West Ballina

completed

completed

V1 - Unara Parkway Drive, Ballina Heights completed completed 
V2 - Compton Drive, East Ballina 4 August N/A
V3 - Fenwick Drive, East Ballina 6 July N/A
V4 - The Serpentine, East Ballina TBC N/A
V5 - Ballina Fair Shopping Centre 9 August N/A

Connect with us

Postal Address

The General Manager
Ballina Shire Council
PO Box 450
Ballina NSW 2478

View more contacts
STREET ADDRESS

40 Cherry Street
Ballina NSW 2478

CUSTOMER SERVICE

Opening Hours

8:15am - 4:30pm

Monday to Friday